Core network infrastructure upgrade at DC3

3 hours
Complete
Complete

The maintenance is now complete. Thanks for your patience.

Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

Scheduled

Engineers are upgrading core network infrastructure for Zettagrid. Network traffic for all Colocated and Full rack customers will be interrupted multiple times for no more than 30 seconds each event. The network interruptions occur as the network traffic switches between primary and secondary paths, both internally (between virtual machines) and externally (to the internet) All virtual machines and services will remain fully operational and automatically restore to normal operations upon completion of the works.

The services impacted include: - VDC-PER09(DC2) Colocation - VDC-PER03(DC3) Colocation/Full Rack - Veeam Backup

If you have any questions about this works or discover issues with your services upon conclusion of the change, contact the Operation Centre by email to support@zettagrid.com or call 1300 597 656 quoting change number CHG-1909

Began at:

Affected components
  • AUS - Western Australia
    • Colocation
    • Veeam Services