Melbourne Core Router Maintenance CHG-884

Monday, 18 October 2 hours and 55 minutes
Complete
Complete

The maintenance is now complete. Thanks for your patience.

Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

Scheduled

Network engineers are performing network maintenance impacting core devices in Melbourne.

During the scheduled maintenance window some customers may experience multiple outages of no more than 2-5 minutes each.

Network traffic for virtual machines, backup and replication services will be interrupted multiple times for no more than 30 seconds each event. All virtual machines and services will remain fully operational and automatically restore to normal operations upon completion of the works.

The services in the Melbourne zone which may be affected include: - Internet and InterCapital Transit - Ethernet Services - MPLS Services - VPS and Virtual Data Centres - Secondsite Replication.

Some customers may need to clear arp tables for the gateway IP, or reboot onsite CPE if services do not restore. If you have any questions about this works or discover issues with your services upon conclusion of the change, contact the Operation Centre by email to support@zettagrid.com or call 1300 597 656 quoting change number CHG-884

Began at:

Affected components
  • AUS - Victoria
    • Compute
    • Ethernet
    • Zerto Services